<?xml version="1.0" encoding="UTF-8"?>
<?xml-stylesheet type="text/xsl" href="https://reports-public.ieso.ca/docrefs/stylesheet/RealtimeTotals_HTML_t1-1.xsl" ?>
<Document docID="RealtimeTotals" xmlns="http://www.ieso.ca/schema" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.ieso.ca/schema https://reports-public.ieso.ca/docrefs/schema/RealtimeTotals_r1.xsd">
<DocHeader>
<DocTitle>Realtime Totals Report</DocTitle>
<DocRevision>1</DocRevision>
<DocConfidentiality>
<DocConfClass>PUB</DocConfClass>
</DocConfidentiality>
<CreatedAt>2026-04-05T18:52:52</CreatedAt>
</DocHeader>
<DocBody>
<DeliveryDate>2026-04-05</DeliveryDate>
<DeliveryHour>19</DeliveryHour>
<Energies>
<IntervalEnergy>
<Interval>1</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>18018.3</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>412.3</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>17606</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>79.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>671.3</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>391.3</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>355.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>15983</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>2</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>17953.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>407.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>17545.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>79.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>671.1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>391.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>355.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>15919.3</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>3</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>18057.1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>408.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>17648.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>79.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>671.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>391.3</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>355.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>16023.1</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>4</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>18079.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>409.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>17669.8</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>79.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>671.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>391.3</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>355.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>16045.6</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>5</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>18084</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>410.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>17673.1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>79.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>663.1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>395.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>359.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>16041.4</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>6</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>18004.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>406.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>17598.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>79.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>671.1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>391.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>355.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>15966.5</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>7</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>17991.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>405</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>17586.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>79.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>670.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>391.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>355.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>15953.5</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>8</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>18009.3</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>405.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>17603.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>79.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>671.1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>391.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>355.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>15977.4</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>9</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>18166.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>413</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>17753.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>79.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>712</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>382.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>323.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>16130.4</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>10</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>18350.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>419.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>17931.3</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>79.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>741.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>374.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>301.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>16316.4</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>11</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>18454.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>419.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>18034.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>79.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>741.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>374.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>301.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>16421.4</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>12</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>18610.1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>425.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>18184.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>79.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>714.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>354.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>348.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>16459.5</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>