<?xml version="1.0" encoding="UTF-8"?>
<?xml-stylesheet type="text/xsl" href="https://reports-public.ieso.ca/docrefs/stylesheet/RealtimeTotals_HTML_t1-1.xsl" ?>
<Document docID="RealtimeTotals" xmlns="http://www.ieso.ca/schema" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.ieso.ca/schema https://reports-public.ieso.ca/docrefs/schema/RealtimeTotals_r1.xsd">
<DocHeader>
<DocTitle>Realtime Totals Report</DocTitle>
<DocRevision>1</DocRevision>
<DocConfidentiality>
<DocConfClass>PUB</DocConfClass>
</DocConfidentiality>
<CreatedAt>2026-09-23T11:52:29</CreatedAt>
</DocHeader>
<DocBody>
<DeliveryDate>2026-09-23</DeliveryDate>
<DeliveryHour>12</DeliveryHour>
<Energies>
<IntervalEnergy>
<Interval>1</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>17373.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>328.8</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>17044.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>305</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>504.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>720.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>192.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>15150.8</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>2</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>17325.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>331.1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>16994.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>305</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>505</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>719.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>193.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>15102.8</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>3</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>17289.3</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>345.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>16944</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>305</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>505</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>719.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>193.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>15064.8</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>4</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>17317.3</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>337.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>16979.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>305</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>505</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>719.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>193.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>15088.8</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>5</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>17310.3</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>335.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>16974.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>305</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>505</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>719.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>193.2</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>15083.8</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>6</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>17315.8</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>334.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>16981.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>305</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>504.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>720.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>192.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>15091.8</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>7</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>17345.8</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>332.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>17013.3</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>305</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>504.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>720.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>192.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>15122.8</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>8</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>17326</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>331.3</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>16994.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>305</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>504.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>720.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>192.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>15096.8</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>9</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>17377.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>332.8</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>17045.1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>305</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>504.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>720.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>192.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>15155.8</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>10</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>17340.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>331.1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>17009.8</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>305</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>504.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>720.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>192.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>15119.8</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>11</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>17300.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>329.5</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>16971.1</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>305</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>504.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>720.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>192.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>15083.8</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
<IntervalEnergy>
<Interval>12</Interval>
<MQ>
<MarketQuantity>Total Energy</MarketQuantity>
<EnergyMW>17192.6</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Loss</MarketQuantity>
<EnergyMW>328.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Load</MarketQuantity>
<EnergyMW>16863.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total Dispatch Load Scheduled OFF</MarketQuantity>
<EnergyMW>305</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10S</MarketQuantity>
<EnergyMW>504.9</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 10N</MarketQuantity>
<EnergyMW>720.4</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>Total 30R</MarketQuantity>
<EnergyMW>192.7</EnergyMW>
</MQ>
<MQ>
<MarketQuantity>ONTARIO DEMAND</MarketQuantity>
<EnergyMW>15043.7</EnergyMW>
</MQ>
<Flag>DSO-RD</Flag>
</IntervalEnergy>
</Energies>
</DocBody>
</Document>