<?xml version="1.0" encoding="UTF-8"?>
<?xml-stylesheet type="text/xsl" href="https://reports-public.ieso.ca/docrefs/stylesheet/TxLimitsOutage0to2Days_HTML_t1-2.xsl" ?>
<Document docID="TxLimitsOutage0to2Days" xmlns="http://www.ieso.ca/schema" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:schemaLocation="http://www.ieso.ca/schema https://reports-public.ieso.ca/docrefs/schema/TxLimitsOutage0to2Days_r1.xsd">
<DocHeader>
<DocTitle>Transmission Facility Outage Limits Report (Days 0 to 2)</DocTitle>
<DocRevision>1</DocRevision>
<DocConfidentiality>
<DocConfClass>PUB</DocConfClass>
</DocConfidentiality>
<CreatedAt>2026-07-15T09:07:00</CreatedAt>
</DocHeader>
<DocBody>
<DateRangeStart>2026-07-15</DateRangeStart>
<DateRangeEnd>2026-07-17</DateRangeEnd>
<TransmissionFacilityData>
<TransmissionFacility>Internal</TransmissionFacility>
<InterfaceData>
<InterfaceName>East-West Transfer East [EWTE]</InterfaceName>
<IssueDate>2026-04-07T08:23:13</IssueDate>
<StartDate>2026-04-02T20:43:00</StartDate>
<EndDate>2026-12-31T23:59:00</EndDate>
<OperatingLimit>475</OperatingLimit>
<Comments>K21W O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>East-West Transfer West [EWTW]</InterfaceName>
<IssueDate>2026-04-07T08:23:13</IssueDate>
<StartDate>2026-04-02T20:43:00</StartDate>
<EndDate>2026-12-31T23:59:00</EndDate>
<OperatingLimit>475</OperatingLimit>
<Comments>K21W O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Flow Into Ottawa [FIO]</InterfaceName>
<IssueDate>2026-05-19T08:59:49</IssueDate>
<StartDate>2026-06-03T15:00:00</StartDate>
<EndDate>2026-09-05T16:00:00</EndDate>
<OperatingLimit>2750</OperatingLimit>
<Comments>Hawthorne T2 O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Madawaska Generation</InterfaceName>
<IssueDate>2026-06-26T11:40:20</IssueDate>
<StartDate>2026-07-05T08:00:00</StartDate>
<EndDate>2026-07-24T16:00:00</EndDate>
<OperatingLimit>240</OperatingLimit>
<Comments>W6CS</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>P502X</InterfaceName>
<IssueDate>2026-07-06T13:12:10</IssueDate>
<StartDate>2026-07-17T08:00:00</StartDate>
<EndDate>2026-07-17T16:00:00</EndDate>
<OperatingLimit>665</OperatingLimit>
<Comments>Hanmer T6 including 500kV Terminal O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Flow North [FN]</InterfaceName>
<IssueDate>2026-07-06T13:12:10</IssueDate>
<StartDate>2026-07-17T08:00:00</StartDate>
<EndDate>2026-07-17T16:00:00</EndDate>
<OperatingLimit>1200</OperatingLimit>
<Comments>Hanmer T6 including 500kV Terminal O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Flow South [FS]</InterfaceName>
<IssueDate>2026-07-06T13:12:10</IssueDate>
<StartDate>2026-07-17T08:00:00</StartDate>
<EndDate>2026-07-17T16:00:00</EndDate>
<OperatingLimit>1460</OperatingLimit>
<Comments>Hanmer T6 including 500kV Terminal O/S</Comments>
</InterfaceData>
</TransmissionFacilityData>
<TransmissionFacilityData>
<TransmissionFacility>Intertie</TransmissionFacility>
<InterfaceData>
<InterfaceName>Ontario-Quebec Bryson 115 kV Import Winter or Summer</InterfaceName>
<IssueDate>2026-03-02T10:20:39</IssueDate>
<StartDate>2025-10-27T07:00:00</StartDate>
<EndDate>2026-12-31T20:00:00</EndDate>
<OperatingLimit>0</OperatingLimit>
<Comments>X2Y O/S at Bryson</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Ontario-Manitoba Export</InterfaceName>
<IssueDate>2026-05-29T15:59:33</IssueDate>
<StartDate>2026-04-02T20:43:00</StartDate>
<EndDate>2026-12-31T23:59:00</EndDate>
<OperatingLimit>50</OperatingLimit>
<Comments>Internal System Conditions</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Ontario-Manitoba Import</InterfaceName>
<IssueDate>2026-05-02T04:18:40</IssueDate>
<StartDate>2026-04-02T20:43:00</StartDate>
<EndDate>2026-12-31T23:59:00</EndDate>
<OperatingLimit>137</OperatingLimit>
<Comments>K21W O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Ontario-Minnesota Export</InterfaceName>
<IssueDate>2026-05-29T15:59:33</IssueDate>
<StartDate>2026-04-02T20:43:00</StartDate>
<EndDate>2026-12-31T23:59:00</EndDate>
<OperatingLimit>50</OperatingLimit>
<Comments>Internal System Conditions</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Ontario-Quebec Maclaren 230 kV Import</InterfaceName>
<IssueDate>2026-06-30T06:49:06</IssueDate>
<StartDate>2026-06-30T07:00:00</StartDate>
<EndDate>2026-07-17T16:00:00</EndDate>
<OperatingLimit>0</OperatingLimit>
<Comments>D5A O/S at Masson</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Ontario-Quebec Maclaren 230 kV Export</InterfaceName>
<IssueDate>2026-06-30T06:50:00</IssueDate>
<StartDate>2026-06-30T07:00:00</StartDate>
<EndDate>2026-07-17T16:00:00</EndDate>
<OperatingLimit>0</OperatingLimit>
<Comments>D5A O/S at Masson</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Quebec Rapide-Ontario (115kV) Import</InterfaceName>
<IssueDate>2026-07-02T12:27:00</IssueDate>
<StartDate>2026-07-17T09:30:00</StartDate>
<EndDate>2026-07-30T16:00:00</EndDate>
<OperatingLimit>0</OperatingLimit>
<Comments>W71D (Widdifield x LN)</Comments>
</InterfaceData>
</TransmissionFacilityData>
</DocBody>
</Document>