<DocTitle>Transmission Facility Outage Limits Report (Days 3 to 34)</DocTitle>
<DocRevision>1</DocRevision>
<DocConfidentiality>
<DocConfClass>PUB</DocConfClass>
</DocConfidentiality>
<CreatedAt>2026-07-13T17:07:01</CreatedAt>
</DocHeader>
<DocBody>
<DateRangeStart>2026-07-16</DateRangeStart>
<DateRangeEnd>2026-08-16</DateRangeEnd>
<TransmissionFacilityData>
<TransmissionFacility>Internal</TransmissionFacility>
<InterfaceData>
<InterfaceName>East-West Transfer East [EWTE]</InterfaceName>
<IssueDate>2026-04-07T08:23:13</IssueDate>
<StartDate>2026-04-02T20:43:00</StartDate>
<EndDate>2026-12-31T23:59:00</EndDate>
<OperatingLimit>475</OperatingLimit>
<Comments>K21W O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>East-West Transfer West [EWTW]</InterfaceName>
<IssueDate>2026-04-07T08:23:13</IssueDate>
<StartDate>2026-04-02T20:43:00</StartDate>
<EndDate>2026-12-31T23:59:00</EndDate>
<OperatingLimit>475</OperatingLimit>
<Comments>K21W O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Flow Into Ottawa [FIO]</InterfaceName>
<IssueDate>2026-05-19T08:59:49</IssueDate>
<StartDate>2026-06-03T15:00:00</StartDate>
<EndDate>2026-09-05T16:00:00</EndDate>
<OperatingLimit>2750</OperatingLimit>
<Comments>Hawthorne T2 O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Madawaska Generation</InterfaceName>
<IssueDate>2026-06-26T11:40:20</IssueDate>
<StartDate>2026-07-05T08:00:00</StartDate>
<EndDate>2026-07-24T16:00:00</EndDate>
<OperatingLimit>240</OperatingLimit>
<Comments>W6CS</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>P502X</InterfaceName>
<IssueDate>2026-07-06T13:16:40</IssueDate>
<StartDate>2026-07-16T08:00:00</StartDate>
<EndDate>2026-07-16T16:00:00</EndDate>
<OperatingLimit>750</OperatingLimit>
<Comments>X504E O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Flow North [FN]</InterfaceName>
<IssueDate>2026-07-06T13:16:40</IssueDate>
<StartDate>2026-07-16T08:00:00</StartDate>
<EndDate>2026-07-16T16:00:00</EndDate>
<OperatingLimit>600</OperatingLimit>
<Comments>X504E O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Flow South [FS]</InterfaceName>
<IssueDate>2026-07-06T13:16:40</IssueDate>
<StartDate>2026-07-16T08:00:00</StartDate>
<EndDate>2026-07-16T16:00:00</EndDate>
<OperatingLimit>760</OperatingLimit>
<Comments>X504E O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>P502X</InterfaceName>
<IssueDate>2026-07-06T13:12:10</IssueDate>
<StartDate>2026-07-17T08:00:00</StartDate>
<EndDate>2026-07-17T16:00:00</EndDate>
<OperatingLimit>665</OperatingLimit>
<Comments>Hanmer T6 including 500kV Terminal O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Flow North [FN]</InterfaceName>
<IssueDate>2026-07-06T13:12:10</IssueDate>
<StartDate>2026-07-17T08:00:00</StartDate>
<EndDate>2026-07-17T16:00:00</EndDate>
<OperatingLimit>1200</OperatingLimit>
<Comments>Hanmer T6 including 500kV Terminal O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Flow South [FS]</InterfaceName>
<IssueDate>2026-07-06T13:12:10</IssueDate>
<StartDate>2026-07-17T08:00:00</StartDate>
<EndDate>2026-07-17T16:00:00</EndDate>
<OperatingLimit>1460</OperatingLimit>
<Comments>Hanmer T6 including 500kV Terminal O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>St. Lawrence West [SLW]</InterfaceName>
<IssueDate>2026-07-13T07:56:42</IssueDate>
<StartDate>2026-07-20T08:00:00</StartDate>
<EndDate>2026-07-20T16:00:00</EndDate>
<OperatingLimit>1220</OperatingLimit>
<Comments>B5D O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Flow Into Ottawa [FIO]</InterfaceName>
<IssueDate>2026-07-13T07:56:42</IssueDate>
<StartDate>2026-07-20T08:00:00</StartDate>
<EndDate>2026-07-20T16:00:00</EndDate>
<OperatingLimit>2500</OperatingLimit>
<Comments>B5D + Hawt T2 O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Wawa MacKay Flow East-230 [WMFE-230]</InterfaceName>
<IssueDate>2026-07-07T10:40:49</IssueDate>
<StartDate>2026-07-21T08:00:00</StartDate>
<EndDate>2026-07-22T16:00:00</EndDate>
<OperatingLimit>375</OperatingLimit>
<Comments>A23P/Mississagi L23-Bus or A24P/Mississagi L24-Bus O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>St. Lawrence West [SLW]</InterfaceName>
<IssueDate>2026-07-13T08:10:20</IssueDate>
<StartDate>2026-07-21T08:00:00</StartDate>
<EndDate>2026-07-21T16:00:00</EndDate>
<OperatingLimit>1220</OperatingLimit>
<Comments>B5D O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Flow Into Ottawa [FIO]</InterfaceName>
<IssueDate>2026-07-13T08:10:20</IssueDate>
<StartDate>2026-07-21T08:00:00</StartDate>
<EndDate>2026-07-21T16:00:00</EndDate>
<OperatingLimit>2500</OperatingLimit>
<Comments>B5D + Hawt T2 O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Sudbury Flow West [SFW]</InterfaceName>
<IssueDate>2026-07-07T10:40:49</IssueDate>
<StartDate>2026-07-21T08:00:00</StartDate>
<EndDate>2026-07-22T16:00:00</EndDate>
<OperatingLimit>713</OperatingLimit>
<Comments>A23P/Mississagi L23-Bus or A24P/Mississagi L24-Bus O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>East-West Transfer East [EWTE]</InterfaceName>
<IssueDate>2026-07-07T10:40:49</IssueDate>
<StartDate>2026-07-21T08:00:00</StartDate>
<EndDate>2026-07-22T16:00:00</EndDate>
<OperatingLimit>325</OperatingLimit>
<Comments>A23P/Mississagi L23-Bus or A24P/Mississagi L24-Bus O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>East-West Transfer West [EWTW]</InterfaceName>
<IssueDate>2026-07-07T10:40:49</IssueDate>
<StartDate>2026-07-21T08:00:00</StartDate>
<EndDate>2026-07-22T16:00:00</EndDate>
<OperatingLimit>350</OperatingLimit>
<Comments>A23P/Mississagi L23-Bus or A24P/Mississagi L24-Bus O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>St. Lawrence West [SLW]</InterfaceName>
<IssueDate>2026-07-13T08:13:59</IssueDate>
<StartDate>2026-07-22T08:00:00</StartDate>
<EndDate>2026-07-22T16:00:00</EndDate>
<OperatingLimit>1220</OperatingLimit>
<Comments>B5D O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Flow Into Ottawa [FIO]</InterfaceName>
<IssueDate>2026-07-13T08:13:59</IssueDate>
<StartDate>2026-07-22T08:00:00</StartDate>
<EndDate>2026-07-22T16:00:00</EndDate>
<OperatingLimit>2500</OperatingLimit>
<Comments>B5D + Hawt T2 O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>St. Lawrence West [SLW]</InterfaceName>
<IssueDate>2026-07-13T08:41:39</IssueDate>
<StartDate>2026-07-23T08:00:00</StartDate>
<EndDate>2026-07-23T16:00:00</EndDate>
<OperatingLimit>1220</OperatingLimit>
<Comments>B5D O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Flow Into Ottawa [FIO]</InterfaceName>
<IssueDate>2026-07-13T08:41:39</IssueDate>
<StartDate>2026-07-23T08:00:00</StartDate>
<EndDate>2026-07-23T16:00:00</EndDate>
<OperatingLimit>2500</OperatingLimit>
<Comments>B5D + Hawt T2 O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Flow Into Ottawa [FIO]</InterfaceName>
<IssueDate>2026-07-13T08:43:55</IssueDate>
<StartDate>2026-07-24T08:00:00</StartDate>
<EndDate>2026-07-24T16:00:00</EndDate>
<OperatingLimit>2500</OperatingLimit>
<Comments>B5D + Hawt T2 O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>St. Lawrence West [SLW]</InterfaceName>
<IssueDate>2026-07-13T08:43:55</IssueDate>
<StartDate>2026-07-24T08:00:00</StartDate>
<EndDate>2026-07-24T16:00:00</EndDate>
<OperatingLimit>1220</OperatingLimit>
<Comments>B5D O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>St. Lawrence West [SLW]</InterfaceName>
<IssueDate>2026-07-13T08:44:49</IssueDate>
<StartDate>2026-07-25T08:00:00</StartDate>
<EndDate>2026-07-25T16:00:00</EndDate>
<OperatingLimit>1220</OperatingLimit>
<Comments>B5D O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Flow Into Ottawa [FIO]</InterfaceName>
<IssueDate>2026-07-13T08:44:49</IssueDate>
<StartDate>2026-07-25T08:00:00</StartDate>
<EndDate>2026-07-25T16:00:00</EndDate>
<OperatingLimit>2500</OperatingLimit>
<Comments>B5D + Hawt T2 O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>St. Lawrence West [SLW]</InterfaceName>
<IssueDate>2026-07-13T08:45:27</IssueDate>
<StartDate>2026-07-26T08:00:00</StartDate>
<EndDate>2026-07-26T16:00:00</EndDate>
<OperatingLimit>1220</OperatingLimit>
<Comments>B5D O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Flow Into Ottawa [FIO]</InterfaceName>
<IssueDate>2026-07-13T08:45:27</IssueDate>
<StartDate>2026-07-26T08:00:00</StartDate>
<EndDate>2026-07-26T16:00:00</EndDate>
<OperatingLimit>2500</OperatingLimit>
<Comments>B5D + Hawt T2 O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Flow Into Ottawa [FIO]</InterfaceName>
<IssueDate>2026-07-13T08:46:05</IssueDate>
<StartDate>2026-07-27T08:00:00</StartDate>
<EndDate>2026-07-27T16:00:00</EndDate>
<OperatingLimit>2500</OperatingLimit>
<Comments>B5D + Hawt T2 O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>St. Lawrence West [SLW]</InterfaceName>
<IssueDate>2026-07-13T08:46:05</IssueDate>
<StartDate>2026-07-27T08:00:00</StartDate>
<EndDate>2026-07-27T16:00:00</EndDate>
<OperatingLimit>1220</OperatingLimit>
<Comments>B5D O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>St. Lawrence West [SLW]</InterfaceName>
<IssueDate>2026-07-13T08:46:58</IssueDate>
<StartDate>2026-07-28T08:00:00</StartDate>
<EndDate>2026-07-28T16:00:00</EndDate>
<OperatingLimit>1220</OperatingLimit>
<Comments>B5D O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Flow Into Ottawa [FIO]</InterfaceName>
<IssueDate>2026-07-13T08:46:58</IssueDate>
<StartDate>2026-07-28T08:00:00</StartDate>
<EndDate>2026-07-28T16:00:00</EndDate>
<OperatingLimit>2500</OperatingLimit>
<Comments>B5D + Hawt T2 O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>St. Lawrence West [SLW]</InterfaceName>
<IssueDate>2026-07-13T08:47:37</IssueDate>
<StartDate>2026-07-29T08:00:00</StartDate>
<EndDate>2026-07-29T16:00:00</EndDate>
<OperatingLimit>1220</OperatingLimit>
<Comments>B5D O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Flow Into Ottawa [FIO]</InterfaceName>
<IssueDate>2026-07-13T08:47:37</IssueDate>
<StartDate>2026-07-29T08:00:00</StartDate>
<EndDate>2026-07-29T16:00:00</EndDate>
<OperatingLimit>2500</OperatingLimit>
<Comments>B5D + Hawt T2 O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>St. Lawrence West [SLW]</InterfaceName>
<IssueDate>2026-07-13T08:48:19</IssueDate>
<StartDate>2026-07-30T08:00:00</StartDate>
<EndDate>2026-07-30T16:00:00</EndDate>
<OperatingLimit>1220</OperatingLimit>
<Comments>B5D O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Flow Into Ottawa [FIO]</InterfaceName>
<IssueDate>2026-07-13T08:48:19</IssueDate>
<StartDate>2026-07-30T08:00:00</StartDate>
<EndDate>2026-07-30T16:00:00</EndDate>
<OperatingLimit>2500</OperatingLimit>
<Comments>B5D + Hawt T2 O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Ontario-Quebec Outaouais 230kV Export </InterfaceName>
<IssueDate>2026-06-30T08:56:24</IssueDate>
<StartDate>2026-07-31T06:00:00</StartDate>
<EndDate>2026-07-31T14:45:00</EndDate>
<OperatingLimit>700</OperatingLimit>
<Comments>A42T</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Ontario-Quebec Outaouais 230kV Import </InterfaceName>
<IssueDate>2026-06-30T08:56:10</IssueDate>
<StartDate>2026-07-31T06:00:00</StartDate>
<EndDate>2026-07-31T14:45:00</EndDate>
<OperatingLimit>605</OperatingLimit>
<Comments>A42T</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>P33C Chats Falls Inflow</InterfaceName>
<IssueDate>2026-07-06T08:23:52</IssueDate>
<StartDate>2026-07-31T06:00:00</StartDate>
<EndDate>2026-07-31T14:45:00</EndDate>
<OperatingLimit>150</OperatingLimit>
<Comments>M32S O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Flow Into Ottawa [FIO]</InterfaceName>
<IssueDate>2026-07-06T08:25:25</IssueDate>
<StartDate>2026-07-31T06:00:00</StartDate>
<EndDate>2026-07-31T14:45:00</EndDate>
<OperatingLimit>1900</OperatingLimit>
<Comments>M32S + A42T + Hawthorne T2 O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Mackenzie Moose Lake Flow West [MMW]</InterfaceName>
<IssueDate>2026-06-25T15:42:22</IssueDate>
<StartDate>2026-08-08T07:00:00</StartDate>
<EndDate>2026-08-20T17:00:00</EndDate>
<OperatingLimit>145</OperatingLimit>
<Comments>F25A/Fort Frances A-Bus/Fort Frances T2 or Mackenzie PL25 Breaker O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>East-West Transfer East [EWTE]</InterfaceName>
<IssueDate>2026-06-25T15:42:22</IssueDate>
<StartDate>2026-08-08T07:00:00</StartDate>
<EndDate>2026-08-20T17:00:00</EndDate>
<OperatingLimit>325</OperatingLimit>
<Comments>F25A/Fort Frances A-Bus/Fort Frances T2 or Mackenzie PL25 Breaker O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Kenora Area Outflow [KAO]</InterfaceName>
<IssueDate>2026-06-25T15:42:22</IssueDate>
<StartDate>2026-08-08T07:00:00</StartDate>
<EndDate>2026-08-20T17:00:00</EndDate>
<OperatingLimit>120</OperatingLimit>
<Comments>F25A/Fort Frances A-Bus/Fort Frances T2 or Mackenzie PL25 Breaker O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Fort Frances Area Inflow [FAI]</InterfaceName>
<IssueDate>2026-06-25T15:42:22</IssueDate>
<StartDate>2026-08-08T07:00:00</StartDate>
<EndDate>2026-08-20T17:00:00</EndDate>
<OperatingLimit>100</OperatingLimit>
<Comments>F25A/Fort Frances A-Bus/Fort Frances T2 or Mackenzie PL25 Breaker O/S</Comments>
</InterfaceData>
</TransmissionFacilityData>
<TransmissionFacilityData>
<TransmissionFacility>Intertie</TransmissionFacility>
<InterfaceData>
<InterfaceName>Ontario-Quebec Bryson 115 kV Import Winter or Summer</InterfaceName>
<IssueDate>2026-03-02T10:20:39</IssueDate>
<StartDate>2025-10-27T07:00:00</StartDate>
<EndDate>2026-12-31T20:00:00</EndDate>
<OperatingLimit>0</OperatingLimit>
<Comments>X2Y O/S at Bryson</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Ontario-Manitoba Export</InterfaceName>
<IssueDate>2026-05-29T15:59:33</IssueDate>
<StartDate>2026-04-02T20:43:00</StartDate>
<EndDate>2026-12-31T23:59:00</EndDate>
<OperatingLimit>50</OperatingLimit>
<Comments>Internal System Conditions</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Ontario-Minnesota Export</InterfaceName>
<IssueDate>2026-05-29T15:59:33</IssueDate>
<StartDate>2026-04-02T20:43:00</StartDate>
<EndDate>2026-12-31T23:59:00</EndDate>
<OperatingLimit>50</OperatingLimit>
<Comments>Internal System Conditions</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Ontario-Manitoba Import</InterfaceName>
<IssueDate>2026-05-02T04:18:40</IssueDate>
<StartDate>2026-04-02T20:43:00</StartDate>
<EndDate>2026-12-31T23:59:00</EndDate>
<OperatingLimit>137</OperatingLimit>
<Comments>K21W O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Ontario-Quebec Maclaren 230 kV Import</InterfaceName>
<IssueDate>2026-06-30T06:49:06</IssueDate>
<StartDate>2026-06-30T07:00:00</StartDate>
<EndDate>2026-07-17T16:00:00</EndDate>
<OperatingLimit>0</OperatingLimit>
<Comments>D5A O/S at Masson</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Ontario-Quebec Maclaren 230 kV Export</InterfaceName>
<IssueDate>2026-06-30T06:50:00</IssueDate>
<StartDate>2026-06-30T07:00:00</StartDate>
<EndDate>2026-07-17T16:00:00</EndDate>
<OperatingLimit>0</OperatingLimit>
<Comments>D5A O/S at Masson</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Quebec Rapide-Ontario (115kV) Import</InterfaceName>
<IssueDate>2026-07-02T12:27:00</IssueDate>
<StartDate>2026-07-16T09:30:00</StartDate>
<EndDate>2026-07-30T16:00:00</EndDate>
<OperatingLimit>0</OperatingLimit>
<Comments>W71D (Widdifield x LN)</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Beauharnois Delivery</InterfaceName>
<IssueDate>2026-07-13T07:56:42</IssueDate>
<StartDate>2026-07-20T08:00:00</StartDate>
<EndDate>2026-07-20T16:00:00</EndDate>
<OperatingLimit>110</OperatingLimit>
<Comments>B5D O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Beauharnois Delivery</InterfaceName>
<IssueDate>2026-07-13T08:10:54</IssueDate>
<StartDate>2026-07-21T08:00:00</StartDate>
<EndDate>2026-07-21T16:00:00</EndDate>
<OperatingLimit>110</OperatingLimit>
<Comments>B5D O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Beauharnois Delivery</InterfaceName>
<IssueDate>2026-07-13T08:13:59</IssueDate>
<StartDate>2026-07-22T08:00:00</StartDate>
<EndDate>2026-07-22T16:00:00</EndDate>
<OperatingLimit>110</OperatingLimit>
<Comments>B5D O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Beauharnois Delivery</InterfaceName>
<IssueDate>2026-07-13T08:41:39</IssueDate>
<StartDate>2026-07-23T08:00:00</StartDate>
<EndDate>2026-07-23T16:00:00</EndDate>
<OperatingLimit>110</OperatingLimit>
<Comments>B5D O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Beauharnois Delivery</InterfaceName>
<IssueDate>2026-07-13T08:43:55</IssueDate>
<StartDate>2026-07-24T08:00:00</StartDate>
<EndDate>2026-07-24T16:00:00</EndDate>
<OperatingLimit>110</OperatingLimit>
<Comments>B5D O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Beauharnois Delivery</InterfaceName>
<IssueDate>2026-07-13T08:44:49</IssueDate>
<StartDate>2026-07-25T08:00:00</StartDate>
<EndDate>2026-07-25T16:00:00</EndDate>
<OperatingLimit>110</OperatingLimit>
<Comments>B5D O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Beauharnois Delivery</InterfaceName>
<IssueDate>2026-07-13T08:45:27</IssueDate>
<StartDate>2026-07-26T08:00:00</StartDate>
<EndDate>2026-07-26T16:00:00</EndDate>
<OperatingLimit>110</OperatingLimit>
<Comments>B5D O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Ontario-New York Import </InterfaceName>
<IssueDate>2026-07-10T09:06:32</IssueDate>
<StartDate>2026-07-27T08:00:00</StartDate>
<EndDate>2026-07-28T16:00:00</EndDate>
<OperatingLimit>500</OperatingLimit>
<Comments>PA302 Beck2 Terminals</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Ontario-New York Export </InterfaceName>
<IssueDate>2026-07-10T09:06:32</IssueDate>
<StartDate>2026-07-27T08:00:00</StartDate>
<EndDate>2026-07-28T16:00:00</EndDate>
<OperatingLimit>650</OperatingLimit>
<Comments>PA302 Beck2 Terminals</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Beauharnois Delivery</InterfaceName>
<IssueDate>2026-07-13T08:46:05</IssueDate>
<StartDate>2026-07-27T08:00:00</StartDate>
<EndDate>2026-07-27T16:00:00</EndDate>
<OperatingLimit>110</OperatingLimit>
<Comments>B5D O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Beauharnois Delivery</InterfaceName>
<IssueDate>2026-07-13T08:46:59</IssueDate>
<StartDate>2026-07-28T08:00:00</StartDate>
<EndDate>2026-07-28T16:00:00</EndDate>
<OperatingLimit>110</OperatingLimit>
<Comments>B5D O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Beauharnois Delivery</InterfaceName>
<IssueDate>2026-07-13T08:47:37</IssueDate>
<StartDate>2026-07-29T08:00:00</StartDate>
<EndDate>2026-07-29T16:00:00</EndDate>
<OperatingLimit>110</OperatingLimit>
<Comments>B5D O/S</Comments>
</InterfaceData>
<InterfaceData>
<InterfaceName>Beauharnois Delivery</InterfaceName>
<IssueDate>2026-07-13T08:48:20</IssueDate>
<StartDate>2026-07-30T08:00:00</StartDate>
<EndDate>2026-07-30T16:00:00</EndDate>
<OperatingLimit>110</OperatingLimit>
<Comments>B5D O/S</Comments>
</InterfaceData>
</TransmissionFacilityData>